Water, H2O, Distilled, Filtered, Purified, Reverse Osmosis, Home RO Units, RO Filters, Water bottle, Water dispenser, Water cooler, Fill, Delivery, Event Water, Wedding Water, Water Store, H2O To Go, Bottled Water, Bottle store, Water Refill, Bottle of Water, Water Filter, Filter Water Bottle, Water Bottles, Hot Water Bottle, BPA Free, Poly Carbonate, PC, Water Dispenser, H2O, H20, Davis, CA, California

News

New Pricing Structure - Better Discounts!

Paul S Taylor

We are updating our pricing structure on March 1st, 2017. Distilled (DS) water is now 70¢/gallon and Reverse Osmosis (RO) is 50¢/gallon. Customers with Water Cards purchased before March 1, 2017 will have 90 days (3/1- 5/31) to buy up to 200 gallons at the current card rates. Our new Water Card structure will now offer customers larger discounts, up to 10% off!

H2O To Go / Davis has made a number of equipment and infrastructure improvements over the last 18 months in order to ensure the highest quality purified water in Davis. (We LOVE giving equipment room tours!) We thank everyone for their support the last 31 years and hope to be here for many more.

Please feel free to contact us during store hours with any questions.

Store Photos 2017 & 2014

Vending Unit Vandalized

Paul S Taylor

After just 4 short days of being in service, the bill acceptor on our 24 Hr Vending Unit was vandalized the night of January 21st. The unit is up and running dispensing Distilled and Reverse Osmosis water. Payment options are currently coin or credit card. We will be servicing this repair in the following months. Thank you for your patience.

2015 Upgrades Phase II • Completed Work Schedule Overview

Paul S Taylor

SUNDAY, DECEMBER 13 (AFTER CLOSE)

  • Shut off & cool down Distiller

  • De-plumb the Equipment Room

  • Disconnect fill table

  • Remove artwork & displays from walls

MONDAY, DECEMBER 14 (DAY 1)

  • Remove & log active inventory

  • Strip equipment room

  • Electrical Panel work start - NO POWER FROM 10AM

  • New copper wiring from breaker room

  • Deconstruct old fill table

  • Prep showroom & equipment room for painting

  • Off-site Inventory

TUESDAY, DECEMBER 15 (DAY 2)

  • Electrical installation - New panel & breakers

  • Paint Showroom & Bathroom

  • Install false walls behind new tables

  • Sketch piping routes on walls and inventory connections

  • Power back on in afternoon

WEDNESDAY, DECEMBER 16 (DAY 3)

  • Final Electrical boxes & conduit

  • Drain work begin for Plumbers

  • Move city feed connection

  • Place fill tables & prep for UV install

  • Install faucet decks on both tables

  • Prep for tile work

  • City inspection - Electrical

THURSDAY, DECEMBER 17 (DAY 4)

  • Rebuild Equipment Room

  • Re-plumb city feed to Distiller (DS) and toReverse Osmosis (RO) Skid

  • Install new flow meter on RO Skid

  • Plumb RO Skid into UV, post-carbon, and storage tank

  • Finish painting

  • Begin tile work

FRIDAY, DECEMBER 18 (DAY 5)

  • Plumb Distiller make tank into UV, post-carbon, and storage tank

  • Plumb transfer pump from RO to DS tank for pressure tank

  • Connect all showroom faucets to new supply lines

  • Begin leak test of pressure lines

  • County health inspection

SATURDAY, DECEMBER 19 (DAY 6)

  • Dry fit of water connection to vending unit

  • Full equipment diagnostics and tests

  • Isolate and repair leaks

  • Final touch ups on painting and tile

  • Transfer showroom inventory back

SUNDAY, DECEMBER 20 (DAY 7)

  • Leak test continues

  • Begin program of vending unit - ELECTRICAL ONLY

  • Polish floor

  • PRIMARY WATER SOFTENER COMPONENT MALFUNCTION

MONDAY, DECEMBER 21 (DAY 8)

  • Order parts for Water Softener repair

  • Application for Yolo County vending unit permit

TUESDAY, DECEMBER 22 (DAY 9)

  • Water Softener repaired

  • Leak test continues

WEDNESDAY, DECEMBER 23 (DAY 10)

  • Leak test complete

  • OPEN FOR BUSINESS